Ivanhoe Electric Announces TBM Acquisition for Santa Cruz Copper Project
What Happened
- On May 11, 2026, Ivanhoe Electric announced it intends to acquire a purpose-built Crossover XRE Tunnel Boring Machine (TBM) and material handling system from The Robbins Company for decline development at the Santa Cruz Copper Project in Arizona. The company secured a legally binding option in March 2026 and notified Robbins of exercise on May 8, 2026; definitive purchase agreements are expected before the end of May 2026.
- The TBM acquisition cost, including refurbishment, is expected to be approximately $64.7 million. Ivanhoe Electric says implementing the TBM will replace planned roadheaders, silica gel grouting and a Railveyor system from the 2025 PFS, with a net increase to initial project capital of less than $20 million. Arrival and assembly onsite are expected Q1 2027, decline development to start Q3 2027, underground development Q3 2028, first oxide ore to heap leach Q4 2028, and first copper cathode production anticipated Q2 2029. The company plans an updated preliminary feasibility study to incorporate the TBM by Q3 2026.
Key Details
- Estimated TBM and material handling system cost: ~$64.7 million (including refurbishment).
- Projected net impact to initial project capital: less than $20 million.
- Schedule: TBM onsite assembly Q1 2027; decline development Q3 2027; 4 km decline expected to be bored in ~12 months; first cathode production expected Q2 2029.
- Regulatory/permits: Site Development Plan approved by the City of Casa Grande (March 2026); TBM method removes need for a Class V Underground Injection Control permit for silica gel.
Why It Matters
- For investors, the TBM purchase is presented as a move to increase certainty and speed of decline development while limiting incremental capital needs (net < $20M). Faster, mechanized decline construction could shorten development timelines versus alternative methods and removes a regulatory hurdle tied to silica-gel injection.
- The company is updating its technical study (PFS) and pursuing project debt financing (including an advanced-stage application with the U.S. Export-Import Bank) and commercial bank discussions, so this decision affects both project engineering and forthcoming financing plans.
- Timelines and cost estimates are forward-looking and subject to risks and change, as noted in the 8-K.