Deep Isolation Nuclear, Inc.: enters $20,000,000 agreement with ARPA-E
What happened
- The filing says Deep Isolation US LLC entered into Modification No. 0001 to Award No. DE-AR0002176 with the Advanced Research Projects Agency–Energy (ARPA-E), finalizing the award as a cooperative agreement effective Nov 19, 2026 and setting the period of performance as Nov 19, 2026 through Nov 18, 2029.
- The filing says the project will demonstrate an integrated system for storing, transporting and disposing of spent nuclear fuel using the Company’s Universal Canister System (UCS) and deep borehole disposal technology through three workstreams: FIRST (first real-world UCS deployment), FILE (U.S. Nuclear Regulatory Commission certification of the UCS) and FUTURE (a non-radioactive deep borehole commercial pilot in Cameron, Texas).
- The filing says the Company issued a press release about the Cooperative Agreement on Nov 23, 2026.
Key details
- Total approved project cost is $47,470,829, of which ARPA-E’s share is up to $20,000,000 (42.13%) and DI US’s required cost share is $27,470,829 (57.87%).
- The approved federal budget is allocated across three budget periods as approximately $17,080,000, $2,870,000 and $60,000; the Recipient Cost Share is allocated as approximately $11,570,000, $10,740,000 and $5,160,000.
- The filing says ARPA-E will reimburse allowable project costs, has substantial involvement in the project, may intervene in or direct technical aspects, and may revise, suspend or terminate the project at Go/No-Go decision points and for noncompliance; payments are on a reimbursement basis.
- The filing says DI US must contribute the Recipient Cost Share in each invoice period, may not use federal funds to meet the cost share, must obtain required NEPA determinations and permits, and must comply with federal reporting, audit and prior-approval requirements; the Company will need to raise additional capital to fund the Recipient Cost Share.
Why it may matter
- Item 1.01 (entry into a material definitive agreement): the filing reports a cooperative agreement with ARPA-E that funds and governs a multiworkstream project to demonstrate the UCS and deep borehole disposal, including federal reimbursement, cost-share obligations, milestones and ARPA-E oversight.
- Item 7.01 (Regulation FD disclosure): the filing reports that the Company issued a press release on Nov 23, 2026 announcing the Cooperative Agreement.