Energy Vault Holdings, Inc.: $78.0 million bridge loan for Sosa project; warrants issued
Accepted (ET)
4:30 PM
Nov 20, 2026
Filed
Nov 20, 2026
Documents
19
Size
4.0 MB
Summary
Energy Vault Holdings, Inc.: $78.0 million bridge loan for Sosa project; warrants issued
What happened
- On Nov 16, 2026, subsidiaries of Energy Vault Holdings, Inc. entered into financing agreements for the approximately 150 MW / 300 MWh Sosa battery energy storage project in Madison County, Texas. The credit agreement with First-Citizens Bank & Trust Company provides a $78.0 million preferred equity bridge loan facility and an $8.7 million letter of credit facility. Bridge borrowings bear interest at Secured Overnight Financing Rate plus 2.00% or an adjusted base rate plus 1.00% and mature no later than Apr 1, 2028.
- A third-party investor agreed to invest $79.6 million in Sosa Partnership, LLC for Class A membership interests, with the first installment equal to 20% of the investor’s commitment and the remainder due by May 30, 2028 (Jun 30, 2028 if extended). On Nov 19, 2026, the bridge loan facility was funded and the Company drew $27.2 million. Also on Nov 19, 2026, OIC Structured Equity Fund I, L.P. funded approximately $38.3 million of its second tranche commitment to Asset Vault.
Key details
- Credit agreement dated Nov 16, 2026: $78.0 million bridge loan, $8.7 million letter of credit, interest at SOFR + 2.00% or adjusted base + 1.00%, maturity Apr 1, 2028; $27.2 million drawn on Nov 19, 2026.
- Investor economics and timing: $79.6 million committed; first installment 20% of commitment; second installment subject to mechanical-completion, project-completion, tax-credit and other conditions and due by May 30, 2028 (or Jun 30, 2028 if extended); 3.80% annual preferred return before distribution flip on the sixth anniversary of placed-in-service date.
- Fees and protections: structuring fee equal to 3% of the investor’s maximum commitment payable at first installment; commitment fee equal to 1% to investor’s parent; tax-equity arranger fee equal to 1.5% of the investor’s commitment (30% payable at closing); repurchase remedy if project not placed in service by Dec 31, 2027 (90-day extension available for a fee equal to 5% of the investor’s commitment), including payment to the investor of 108% of funded contributions plus unpaid expenses if repurchase proceeds are not timely.
- Unregistered equity issuance: in connection with OIC’s $38.3 million contribution, the Company issued warrants to purchase up to 6,089,009 shares of common stock at an exercise price of $4.080375 per share.
Why it may matter
- The filing reports Item 1.01 (entry into a material definitive agreement) describing the Sosa project financing and related partnership arrangements, Item 2.03 (creation of a direct financial obligation) reflecting the bridge loan, and Item 3.02 (unregistered sale of equity securities) covering issuance of warrants to OIC. This filing does not show why the insider traded or why the company acted.